Inside the Hunterston Close: How a 400 MW Battery Got Financed Without a Single Buyer
On September 24, four banks agreed to lend against a 400-megawatt Scottish battery that has no single buyer for its power, and the way they got comfortable doing it says a lot about where project finance is headed.
The Deal
On September 24, Revera Energy reached financial close on Hunterston, a 400-megawatt, 800-megawatt-hour battery storage system in North Ayrshire, Scotland, roughly 50 kilometers southwest of Glasgow (Energy-Storage.News, 2026). The project connects directly to the transmission network, can discharge full output for two hours, and construction began immediately once a notice to proceed was issued the same day. Commercial operations are targeted for the third quarter of 2028. Revera took its final investment decision on the project back in June, so what closed in September was the financing itself: a non-recourse loan syndicated across four banks, Santander, Barclays, Commonwealth Bank of Australia, and NatWest (Solar Power Portal, 2026). The precise size of the debt has not been disclosed, but the structure behind it, and the year that led up to it, offers a clean, current example of how project finance actually gets a technology like standalone storage over the line.
Why Non-Recourse
Was the Right Tool
Revera did not borrow against its own corporate credit. Hunterston sits inside its own standalone legal entity, and the four lending banks can look only to that entity’s own cash flow for repayment, not to Revera’s wider balance sheet or its other projects. This is what non-recourse project finance means in practice, and it is the same structural choice that financed most of the world’s wind and solar fleet over the past two decades. It lets a developer raise the capital one project needs without staking the company that built it, and it lets a bank underwrite one specific, well-defined risk rather than the sprawling risk of an entire corporation. What makes Hunterston notable is that lenders were willing to extend that same non-recourse structure to a battery, an asset that, unlike a wind or solar farm, does not sell its output under one simple long-term contract.
The Problem Every Battery Faces
A solar or wind farm can sign a single long-term power purchase agreement and hand lenders a clean, contracted revenue line to underwrite. A battery cannot, because it does not generate power to sell under one contract. It earns money instead by shifting electricity in time and by stacking several distinct, often short-term revenue streams: buying power when it is cheap and selling when it is expensive, providing capacity that a grid operator pays for being available, and supplying fast-responding balancing products such as Dynamic Containment and Dynamic Regulation that keep the grid stable minute to minute. Every one of those revenue streams is smaller and more volatile than a single power purchase agreement, and none of them alone would normally support the kind of debt Hunterston needed. That is the problem project finance had to solve here, and it is the same problem facing every standalone battery project trying to reach financial close.
How Hunterston Got Bankable Anyway
Revera solved it by handing each piece of risk to whichever counterparty was best placed to carry it. bp took on a long-term tolling structure, effectively paying for the right to operate the battery and absorbing the volatility of wholesale and balancing market prices. Danske Commodities layered a long-term revenue floor on top, guaranteeing a minimum level of income regardless of how the market performs, with any upside above that floor shared between the project and the optimizer (Energy-Storage.News, 2026). Together, the tolling structure and the floor gave lenders something they could underwrite: a stable, contracted floor for debt service, rather than a bet on merchant power prices four years out.
| Counterparty | Role | Risk it absorbed |
| bp | Long-term tolling and optimization | Wholesale and ancillary-service price risk |
| Danske Commodities | Revenue-floor and trading arrangement | Downside revenue risk below the floor |
| Sungrow | Battery supply and long-term servicing | Technology and performance risk |
| OCU Group | Balance-of-plant contractor and O&M | Construction and operating risk |
None of these contracts eliminate risk. They relocate it to whichever party can price and manage it best, which is precisely what turns a technically excellent but commercially unproven asset into something four separate banks are willing to lend against.
Part of a Bigger Bet
Hunterston is not one off. It is the second of three transmission-connected Scottish batteries Revera is financing in 2026, following the 200-megawatt Windyhill project, which closed in February, with a third project, Kincardine, expected to start construction in early 2027. Together, the three total nearly 1 gigawatt and 2 gigawatt-hours of storage and more than 500 million pounds of planned investment, all backed by equity from the Carlyle Group (Renewables Now, 2026). Financing three large batteries in the same region within a single year is itself a form of risk management. A single project lives or dies on one local market’s prices; a small portfolio spreads that same exposure across more than one asset and, over time, more than one revenue mix, giving both the sponsor and its lenders a steadier base to build on as each new project closes.
Why This Matters
A few years ago, a standalone battery with no long-term offtake contract would have struggled to raise non-recourse debt at all. Hunterston shows what changed: not the underlying merchant risk, but the contractual architecture built around it. A tolling agreement with an energy major, a revenue floor from a specialist trader, and equipment and construction risk handed to experienced counterparties turned an unconventional revenue profile into something four banks could underwrite together. Real risks remain for the wider Scottish buildout, from grid connection queues to unresolved questions about how Britain's electricity market rules will evolve, and those will shape how quickly this template gets repeated. But Hunterston is a working example of project finance extending its reach to exactly the kind of asset the grid needs most and traditional financing structures were never built for.
References
Energy-Storage.News. (2026, September 23). Carlyle-backed Revera secures financing for 800 MWh Scottish battery. https://www.ess-news.com/2026/09/23/carlyle-backed-revera-secures-financing-for-800-mwh-scottish-battery/
Power Technology. (2026, September 24). Danske Commodities to optimise Hunterston BESS project in UK. https://www.power-technology.com/news/danske-optimise-hunterston-bess/
Renewables Now. (2026, September 24). Revera closes funding for 400-MW Hunterston BESS in Scotland. https://renewablesnow.com/news/revera-closes-funding-for-400-mw-hunterston-bess-in-scotland-1301763/
Solar Power Portal. (2026, September 24). Revera finances, begins construction of 400MW Scottish BESS. https://www.solarpowerportal.co.uk/battery-storage/revera-closes-financing-begins-construction-of-400mw-scottish-bess